Portfolio

Bailey Bridge Rehabilitation

About This Project

This was the rehabilitaion of the footing structure of this bailey bridge.  We jacked whole structure up and then replaced woooden sills that were deteriating with concrete sills.

Location:
Summit Creek, near Creston

In order to refurbish the ends of the bridge the whole structure was jacked up.  Then the deteriorated wood sills were removed and replaced with concrete sills.  The bridge was then lowered onto the new foundation.  The ballast walls re re-installed, back filled and compacted.  This procedure was repeated for the other end of the bridge.





Principal Client:
Creston Valley Wildlife Management Authority
Contact Name:
Don Bjarnason